The federal government has threatened to mete out a stiff sanction to the China Civil Engineering and Construction Company (CCECC) over the firm’s alleged failure to provide 85 per cent counterpart fund for the the rail project in some parts of the country.

The Minister of Transportation, Muazu Sambo, decried the slow pace of work in the Kanu-Kaduna and Maiduguri-Port Harcourt rail lines.

Sambo gave the warning on Saturday while briefing journalists in Lagos at the end of a tour of the Lekki Deep Seaport to ascertain the level of work done so far.

Sambo, who frowned at the attitude of the Chinese firm, said two years after the agreement was signed, CCECC had not provided any of its 85 per cent counterpart fund.

According to him, the agreement stipulates that CCECC is to provide 85 per cent of the project cost while the federal government provides the remaining 15 per cent.

He said, “I have given them till October 2022 to fulfill their own part of the agreement or stiff sanction would be meted out to them.

“How could it be said that two years after the agreement was signed, CCECC is yet to provide a dollar?”

Recall that former Minister of Transportation, Rotimi Amaechi, had in March accused the firm of playing politics with the Kanu-Kaduna rail project, urging the contractor to provide funding for the project.

Amaechi had said, “The pace is extremely slow, the equipments are supposed to be 2,000 plus, but what they (CCECC) have brought so far is 541, they claim that 300 and something equipment are in Kaduna. I will send people to check. Even if you add that all together, you will have 800 and something equipment in place of 2,000 equipment that they are supposed to bring. That means something is wrong somewhere.

SEE ALSO:  IPOB begins cleansing, arrest of terror gangs in S’East

“I know they (CCECC) claim that there is no money, that we have not funded them. But what of their responsibility in the contract that they will look for the money?

“CCECC has not brought money, the Chinese are no longer giving us money for more than three to four years now. So CCECC can’t afford to delay in their responsibility to look for money for the project. That is what the Chinese must do.”

Advertisements
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

News

PDP demands probe of Supreme Court fire disaster

Published

on

The Peoples Democratic Party, (PDP) has demanded a thorough investigation into the fire incident that gutted a section of the Supreme Court in the early hours of Monday.

The party raised the alarm over the incident which it described as suspicious giving the fact that a verdict on a sensitive issue of national importance is being expected.

National Publicity Secretary of the party, Debo Ologunagba made the position of the opposition party on the fire incident known in a statement on Monday.

He said, “The PDP is worried over the fire outbreak especially given heightened public apprehension of possible arsonist attack with the intent to cripple and frustrate the Supreme Court from effectively discharging its constitutional duties especially with regard to high profile electoral cases including the Presidential Election Appeals pending before it.

“Our Party demands for an immediate full-scale investigation into the fire outbreak with the view to unraveling the circumstances or possible sabotage in the incident.

“The PDP insists that the outcome of the investigation should be made public unlike those of previous fire incidents in various government Ministries, Departments and Agencies which were characteristically swept under the carpet by the All Progressives Congress (APC) administrations.

“While calling on the Federal Government to beef up security around the Supreme Court, the PDP also demands that Nigerians must be assured of the safety of sensitive documents and equipment at the Court especially at this critical time.”

Advertisements
SEE ALSO:  Ex-RCCG pastor, Laoye installed as Soun, begins seven-day rites
Continue Reading

News

Gov. Mbah tasks FG on New Road Maintenance Model as bridge collapses along Enugu-Port Harcourt Expressway

Published

on

Gov Peter Mbah (centre) and some government officials during inspection of the collapsed bridge in Enugu on Monday

…urges FG to concession roads to states

Governor of Enugu State, Dr. Peter Mbah, has called for a new road maintenance model to guarantee a better condition and longevity of Nigerians roads, regretting that the current model had failed woefully.

Dr. Mbah made the call when he visited the site of the collapsed bridge between the New Artisan flyover and the NNPC Mega Station along the Enugu – Port Harcourt Expressway.

The collapsed bridge

Fielding questions from newsmen after the first-hand inspection of the scene of the disaster, Mbah who thanked God that no life was lost despite the magnitude of the incident, urged the federal government to consider a concession of all the federal roads in each state to the state governments for proper maintenance in conjunction with the private sector.

“I think the question should be whether the current model of federal road maintenance is working or not; and I think that is the bigger question that we must ask.

“Today, we are here witnessing a tragedy that has just occurred. We are fortunate enough that no life was lost, but this could have been prevented entirely. So, the people can no longer ply this route because of this tragedy. This shows clearly that we do not have a sound federal road maintenance model.

“The bridge collapse didn’t just happen. These threats could have been identified if we had routine or regular maintenance.

“Perhaps the way to go is to find a way to concession these roads to the states. The states need to take charge of the roads within their domains and there has to be a conversation around the funding models”.

SEE ALSO:  Asari Dokubo responsible for killings in South-East – IPOB alleges

Gov Mbah (R) inspecting the collapsed New Artisan Enugu bridge that collapsed on Monday

The said bridge collapsed on Monday, leaving commuters stranded.

Meanwhile, in a statement signed by the Enugu State Commissioner for Works and Infrastructure, Engr. Gerald Otiji, government has advised commuters to use Nza Street through New Haven or ply Ogui Road and Abakaliki Road to their various destinations, while the authorities come up with measures for immediate repair on the failed section of the bridge.

Advertisements
Continue Reading

News

Flyover bridge collapses in Enugu, no casualty

Published

on

The collapsed flyover bridge in Enugu
The flyover bridge across the Enugu – Port Harcourt Expressway at the Enugu New Artisan market in Enugu state capital has collapsed.

The bridge collapsed Monday morning but an eyewitness said there was no casualty as artisans and residents were yet to come out from their homes for the day’s activity.

The eyewitness, an Auto Mechanic who identified himself as Nnamdi, told The Advocate that two lorries conveying goods which were on the bridge when the incident occurred were affected.

According to him, drivers and conductors of the two lorries, however, escaped unhurt.

The Advocate observed that one lane of the Enugu – Port Harcourt dual-carriage way had been blocked by the debris of the collapsed bridge forcing motorists playing the expressway to divert through alternative routes to continue their journey.

Security operatives, officials of the Federal and Enugu State Ministries of Works, Federal Road Maintenance Agency, Federal Road Safety Commission (FRSC) were sighted within the area to access the situation as well as to assist the road users plying the alternative routes.

Residents of Goshen Estate, Premier Layout, worshippers at the Dunamis Church and traders at the New Artisan market who are regular users of the bridge are likely to encounter serious traffic gridlock on account of the collapsed bridge, if an alternative route is not created as a matter of urgency.

The state government has yet to speak on the development by press time.

Advertisements
SEE ALSO:  I’ve fulfilled my promise on Boko Haram — Buhari
Continue Reading

Trending